Welcome to Future Star Machinery & Equipment International Trade Co., Ltd.

Pile Cutting Machine Concrete Pole Pile Cutting Machine CLAMP MATI 200/350/500/600/700/800/1000

POWER: 4KW
SPEED: 1435r/MIN
POWER: 380V

TYPE: HXG132S-4
POWER: 5.5KW
SPEED: 1440r/MIN
POWER: 380V

TYPE: HXG132S-4
POWER: 5.5KW
SPEED: 1440r/MIN
POWER: 380V

1. There must be no high-voltage lines in the pile driver operation area. The operation area should be clearly marked or fenced and unauthorized persons are not allowed to enter. The operator shall monitor the pile hammer during the piling process at a distance of 5 m from the center of the hammer.
2. The diesel piling hammer shall use fuel with the specified mixing ratio, and the fuel tank shall be filled and the drain valve shall be opened before operation.
3. Before operation, the air screw should be opened to exhaust the air in the oil circuit, and the fuel pump should be checked and tested, and the fuel injection should be observed from the cleaning hole.
4. Before operation, the upper piston should be lifted slightly above the upper cylinder by means of a landing gear, and the oil plug of the oil storage chamber should be opened and filled with lubricating oil according to regulations.
5. For the newly opened pile hammer, 0.5L lubricating oil should be poured along the upper piston one week in advance, and a certain amount of lubricating oil should be added to the lower piston with an oil gun.
6. All fastening bolts must be checked.
7. After lifting the pile hammer out of the anvil, its slide length should not exceed 200mm, if it exceeds, the buckle of the pile cover rope should be adjusted.
8. the wear gap of the guide plate should be checked, and it should be replaced if the gap exceeds 7mm.
9. should check the buffer pad, when the anvil seat and rubber pad contact surface is less than 2/3 of the original area, or under the cylinder flange and anvil seat gap is less than 7mm, should replace the rubber pad.
10. For water-cooled pile hammers, the water tank must be filled with water.
11. Before starting pile hammering, the hammer, pile cap and pile should be on the same axis, and the pile should not be moved eccentrically.
12. When starting pile hammer in soft soil layer with large pile penetration, the throttle should be closed first for cold blows, then open the throttle to start pile hammer when the penetration of each blow is less than 100mm.
13. After the piles are inserted, the verticality of the piles should be corrected in time.
14. In piling, the jump height of the upper piston must not exceed that specified in the instruction manual.
15. When the upper piston falls and the diesel hammer does not start, the upper piston may have a short bumpy period, at this time the landing gear should not fall, and should prevent it from hitting the touch block.
16. During the stacking process, there should be a person responsible for pulling the control rope on the crank arm.
17. When the upper piston is disengaged from the starting hook, the landing gear should continue to be lifted, and it is desirable to make it reach or exceed a distance of 2 m from the upper cylinder.
18. During operation, the focus should be on whether the upper piston lubricating oil leaks out of the oil hole.
19. During operation, when the impact energy of the pile hammer reaches the energy, the hammer penetration value ***10 shall not be less than 5mm.
20. The packing in the pile cap shall not be skewed and the center of the pile cap shall be hammered during operation.

Product Description

POWER: 4KW
SPEED: 1435r/MIN
POWER: 380V

TYPE: HXG132S-4
POWER: 5.5KW
SPEED: 1440r/MIN
POWER: 380V

Specifications
TYPE: HXG132S-4
POWER: 5.5KW
SPEED: 1440r/MIN
POWER: 380V

1. There must be no high-voltage lines in the pile driver operation area. The operation area should be clearly marked or fenced and unauthorized persons are not allowed to enter. The operator shall monitor the pile hammer during the piling process at a distance of 5 m from the center of the hammer.

2. The diesel piling hammer shall use fuel with the specified mixing ratio, and the fuel tank shall be filled and the drain valve shall be opened before operation.

3. Before operation, the air screw should be opened to exhaust the air in the oil circuit, and the fuel pump should be checked and tested, and the fuel injection should be observed from the cleaning hole; if any abnormality is found, adjustment should be made.

4. Before operation, the upper piston should be lifted slightly above the upper cylinder by using the landing gear, and the oil plug of the oil storage chamber should be opened and filled with lubricating oil according to regulations. For the automatic lubrication of the pile hammer, a special oil pump should be used to add lubricating oil to the lubricating oil pipe, and the air in the pipe should be removed. 5.

5. For the newly opened pile hammer, 0.5L lubricating oil should be poured along the upper piston one week in advance, and a certain amount of lubricating oil should be added to the lower piston with an oil gun.

6. All fastening bolts should be checked, and the fastening bolts of the guide plate should be specially checked, and no operation should be carried out with loose and missing parts.

7. should check and confirm the working mechanism of landing gear ***, starting hook and upper piston contact line between 5~10mm.

8. After lifting the pile hammer out of the anvil, its slide length should not exceed 200mm, if it exceeds, the buckle of the pile cover rope should be adjusted.

9. the wear gap of the guide plate should be checked, and it should be replaced if the gap exceeds 7mm.

10. should check the buffer pad, when the anvil seat and rubber pad contact surface is less than 2/3 of the original area, or under the cylinder flange and anvil seat gap is less than 7mm, should replace the rubber pad.

11. For water-cooled pile hammers, the water tank must be filled with water. Soft water should be used for cooling water. Warm water should be added in winter.

12. Before starting pile hammering, the hammer, pile cap and pile must be on the same axis, and the pile must not be moved eccentrically.

13. When starting pile hammer in soft soil layer with large pile penetration, the throttle should be closed first for cold blows, then open the throttle to start pile hammer when the penetration of each blow is less than 100mm.

14. After the piles are inserted, the verticality of the piles should be corrected in time. If the pile is more than 3m into the ground, it is strictly forbidden to correct the slope of the pile by walking with a pile driver.

15. In piling, the jump height of the upper piston shall not exceed that specified in the instruction manual. The visual determination of the height shall be in accordance with the visual table or calculation formula in the manufacturer's instruction manual. When the specified height is exceeded, the throttle should be reduced to control the falling distance.

16. When the upper piston falls and the diesel hammer does not start, the upper piston may have a short bumpy period, at this time the landing gear should not fall, and should prevent it from hitting the touch block.

17. During the stacking process, there should be a person responsible for pulling the control rope on the crank arm; in case of an accident, the control rope can be used to stop the hammer in case of an emergency.

18. When the upper piston is disengaged from the starting hook, the landing gear should continue to be lifted, and it is desirable to make it reach or exceed a distance of 2 m from the upper cylinder.

19. During operation, the focus should be on whether the upper piston lubricating oil leaks out of the oil hole. When the lower cylinder is lubricated by an automatic oil pump, the oil pipe head should be opened frequently to check whether there is oil discharge; when there is no automatic oil pump, lubricating oil should be injected into the lubrication point of the lower piston every 15 minutes. When the pile is driven in for more than 15 minutes, lubricating oil should be added immediately after the pile is driven in.

20. During operation, when the impact energy of the pile hammer reaches the energy, the hammer penetration value ***10 shall not be less than 5mm.

21. The packing in the pile cap shall not be skewed and the center of the pile cap shall be hammered during operation.

22. During operation, when the water in the water jacket is lower than the suction and discharge ports of the lower cylinder due to evaporation, it should be replenished in time, and it is strictly forbidden to operate without water.

23. All sha operations

Why should you shop at PT. FUTURESTAR INDONESIA?
1. We are FIRST HAND IMPORTERS, so our prices are very competitive.
2. Customers can COME to our store if they want to see the product in person.
3. Serving orders in LARGE / GROWING AMOUNTS

Related Products

Leave a Reply

Email
Email: sales@ptfuturestar.com
WhatsApp
WhatsApp Me
WhatsApp
WhatsApp Me
WhatsApp